About us
Chairman's Message
Events & Activities
List of Committee
Safety Alert & Message
Photo Album
Safety
Links
 
Events / Activities
 

 
Site Visit: L2 Contract for Lyric Theatre Complex, District Cooling System and Extended Basement
 


Date, time & venue

2022-12-10;09:00 - 12:00;Lyric Room 9/F., Tower 2 China Hong Kong City, No. 33 Canton Road, Tsim Sha Tsui, Kowloon

Organizers

Safety Specialist Committee (SSC), Jointly Organization with Building Services Division


Docoument:

L2 Site walk.pdf


Project Introduction:

Located at West Kowloon Reclamation Area with an area of 40-hectare, the WKCD is developing an integrated arts and cultural district with world-class facilities and iconic architecture for locals and tourists. It is one of the world’s largest and most ambitious arts and cultural building programmes that will deliver up to 17 cultural and arts facilities, open spaces, education, commercial and retail facilities as part of a new cultural hub being developed with funding from the HKSAR Government.

 

There are more than 70% of MEP installations by DfMA or MIMEP design and hot-work-free installation methodology to achieve high safety and quality performance. With the introduction of DCS and other sustainable features, it will serve as a showcase of Hong Kong with long-term sustainability. Estimated design capacity of DCS plant is 70MW. The master plan of WKCD DCS Central chiller plant of WKCD DCS is allocated in the basement by integrating with the master planning of the district. The chilled water will be distributed to the DCS customer substation by a 2-pipe ring circuit with different sizes of 3-pipe tee-off chilled water pipe connection housed inside specified services corridor or trench in the basement. The DCS pipe network will be extended by phases to follow the pragmatic approach of the WKCD development.

 

Programme Highlights:  

1.      70MW (22,500RT) Sea Water Cooled DCS for WKCDA developments

2.      9 x 2,500RT chillers

3.      D.I. seawater pipes up to DN1.6m

4.      Chilled water pipes up to DN1.2m

5.      >840Ton steel pipes

6.      Zero Hot Work on site

7.      >70% DfMA/MiMEP works

8.      Removed 70% site activities

9.      Completed 80% work in 11 months

10.   Full BIM from design development, construction information, DfMA/MiMEP production to O&M

11.   Digital management for RICS inspection with RSS

12.   Zero accident since the DCS work commencement

 

 

CPD Certificate:

Electronic copy of CPD Certificate will be delivered to participants (who have attended for more than half of the session) within one month after the online forum conducted.

 

Registration:

Priority will be given to members of HKIE SSC. Vacancy will be accepted on a first-come-first-served basis. The maximum number of participants is 15. For registration, please click here. Successful members will be notified by an e-mail with a meeting link few days before the event. For ease of effective communication in the forum, we would be very grateful if you would enter your HKIE membership number and name (same as registration name) when joining the online session.

 

Enquiries:

For enquiries, please contact Ms Constance Wu (constance.wu@clp.com.hk)






Report

 
 

 
 

 

 
 
  Home | Contact Us | Copyright | Privacy Policy | Disclaimer | SitemapAdmin
Copyright ©2008 The Hong Kong Institution of Engineers. All rights reserved.